Attendance - Pete
Tunner, Judy Smith, Ron Allen, ?
Discussion
-
Pete brings up the three best ways to proceed with building:
(1)Traditional (2). Design Build (3). Negotiated Contract. The
committee felt like with the information we have, to go with
Negotiated Contract.
-
Pete to talk with Mr. Black to get proposal.
-
Scott and Steve to report back on what other
churches have done in there building of new facility.
-
What is the charge of this committee? Decided
to present to church the three ways to proceed. Business meeting on
11/15/06.
-
Pete to contact three contractor's and report back.
|